Rebuild Projects

At Enersource, we're always rebuilding our distribution infrastructure to maintain world class system reliability for our customers.

Making sure residents stay informed is one of our top priorities.  Customers in rebuild areas will receive advance notification prior to the start of a project about the time and duration of the project and all planned power outages.  It's our intention to carry out this work with the least possible inconvenience to residents.

View our map of Mississauga to see what areas we have rebuilds scheduled in this summer. 

If there is a rebuild near you, the number on the map will correspond with one of the rebuilds listed below if there is more information available at this time.  We update this page regularly as rebuilds progress, so there may be more information available at a later date.

 

Underground Projects

 

May 2010

1) Windwood - Enersource crews are working on trenching and directional boring in this area.  Work is ongoing and is expected to finish in August 2010.  View the information package.

2) City Centre Drive - Work is ongoing as crews continue to replace cables to local commercial buildings.

3) Parmeer - In the area of Glengarry / Cedarglen / Claymore and Parmeer, work is ongoing as service ducts are installed and converted by July.  View the information package.

 

July 2010

4) Mainroyal - This project is on track to begin in mid-July.  Check back for more details later on!

 

August 2010

5) Montevideo - This project is on track to begin in August!  Check back for more details later on!